Quang Ninh Budget Audit: Recommendations to Address More Than VND 54.8 Billion

22/10/2026 - 09:45      37 view
The audit of local budget management and the 2025 local budget finalization report of Quang Ninh Province (now Quang Ninh City) identified several shortcomings in budget estimation, allocation, expenditure management, monitoring of salary reform funds, and the implementation of public investment projects. The State Audit Office of Vietnam (SAV) recommended financial adjustments totaling more than VND 54.8 billion and called for corrective measures to address shortcomings in the management and use of public finances.
Nội dung chính[ẩn][hiện]

The SAV announces the audit results of local budget management and the 2025 local budget finalization report of Quang Ninh Province. Photo: M. Thuy

Shortcomings in Capital Allocation and Budget Expenditure Management

The audit report noted that the management and administration of state budget revenues and expenditures, the allocation and adjustment of public investment capital plans, and the management and implementation of investment projects in Quang Ninh Province were generally conducted in accordance with regulations. However, the SAV identified several shortcomings in budget estimation and assignment, resource allocation, and budget management and utilization.

Specifically, the Provincial People's Committee allocated VND 20 billion for investment preparation and planning tasks before the relevant lists of projects, tasks, and estimates had been approved in accordance with regulations.

Regarding commune-level budgets, the Provincial People's Council issued norms for allocating development investment expenditure estimates without having established sufficient allocation criteria and calculation bases or completed an assessment of actual infrastructure needs at the commune level, including transport infrastructure, cultural facilities, and urban improvement, under the two-tier local government model. In addition, the capital allocation objectives specified in Resolution No. 308/NQ-HDND dated October 17, 2025, issued by the Provincial People's Council, and Decision No. 3943/QD-UBND were not fully consistent.

Another notable issue concerned the organization of artistic programs and events serving political objectives and tourism development without fully established expenditure norms. A sample audit of the Ha Long Concert 2025 artistic program found that 64 out of 77 work and service items lacked the required economic-technical norms, expenditure norms, or unit prices for public services funded by the state budget.

The SAV recommended that the Provincial People's Committee direct relevant agencies to review the organization and payment of expenditures for which no applicable norms had been established. Where wastefulness was identified, the causes and responsibilities should be clarified and handled in accordance with regulations. The SAV also recommended that the Provincial People's Council consider issuing expenditure regulations and norms for the cultural and tourism sectors as a basis for budget estimation and expenditure control, ensuring thrift and preventing waste.

In state budget revenue management, tax debt recovery had not achieved the targeted results. As of December 31, 2024, the recovery rate for collectible tax arrears stood at only 42.5%, below the target of 80%. In addition, communes, wards, and special administrative units had not returned VND 40.936 billion to the provincial budget in targeted supplementary funding for which the spending purposes had been completed.

Regarding the carryover of expenditures, Quang Ninh had not carried forward VND 20.8452 billion in savings from the 5% reduction in recurrent expenditure to 2026 for continued monitoring and use, as required under Resolution No. 119/NQ-CP dated August 7, 2024. The provincial salary reform fund, amounting to VND 680.449 billion, had also not been carried forward in accordance with regulations and remained recorded as part of the budget surplus.

In construction investment, a detailed audit of 51 projects managed by 10 project owners found that project management and implementation generally complied with regulations. However, the SAV identified shortcomings in the formulation, appraisal, and approval of investment policies and projects; design and cost estimation; contractor selection; contract management; construction quality and progress management; acceptance, payment, and finalization.

Notably, for certain project components, the quantities accepted and paid for had been calculated inaccurately compared with as-built documentation and construction drawings. The audit identified downward adjustments totaling VND 11.009 billion.

Some projects required adjustments to their implementation periods or experienced delays compared with their approved schedules. Difficulties in site clearance and delays in handing over sites to contractors affected implementation progress and disbursement at several projects.

Recommendations for Financial Adjustments and Improvements in Public Investment Management

Based on the audit findings, the SAV recommended total financial adjustments of VND 54,802,322,754, comprising an increase in state budget revenue of VND 1,054,830,489 and the recovery or reduction of state budget expenditure totaling VND 53,747,492,265.

In addition to these financial recommendations, the SAV issued several recommendations concerning the management and monitoring of funding sources. Regarding the salary reform fund, the SAV recommended monitoring and making additional provisions of VND 927,632,789; bringing VND 680,449,000,000 under the management and monitoring of the salary reform fund for carryover purposes; and adding VND 27 billion to the amount subject to management and monitoring in accordance with regulations. These recommendations aim to ensure that funding sources are fully accounted for, used for their intended purposes, and monitored separately from the total financial adjustments stated above.

In construction investment, the SAV recommended that Quang Ninh Provincial Area I Construction Investment Project Management Board recover VND 1,402,592,677, representing the difference between the amount disbursed and the finalized value of two projects. Of this amount, VND 248,965,000 relates to the An Tiem Road project, running through Viet Hung Industrial Park to Van Yen intersection, while VND 1,153,627,677 relates to the access road to Ben Rung Bridge within Quang Ninh Province.

For Quang Ninh Provincial Area II Construction Investment Project Management Board, the SAV recommended that the project owner coordinate with relevant parties to address, in accordance with regulations, a downward adjustment of VND 558,579,361 relating to a lump-sum contract package.

The SAV also recommended that project owners and relevant entities review and address a downward adjustment of VND 20,020,768,499 in the remaining contract value to ensure that payments comply with regulations and prevent losses to the state budget.

Alongside the financial adjustments, the SAV recommended corrective measures to address shortcomings in the management and use of public finances and public assets, and to clarify the responsibilities of the relevant agencies and units.

Notably, the SAV recommended that the Quang Ninh Provincial People's Committee direct relevant units to inspect and review the payment of VND 3.214 billion by Cua Ong Ward People's Committee for environmental sanitation services along National Highway 18, on the Ha Long–Mong Duong section, which is operated under a build-operate-transfer (BOT) contract.

The SAV had previously raised this issue during a thematic audit of the management and use of environmental protection and climate change response funding in Quang Ninh Province for the 2021–2023 period. Accordingly, the SAV reiterated its recommendation that the locality inspect, review, and implement the previous recommendation to prevent waste and losses to the state budget.

Regarding shortcomings in the allocation of investment capital to communes under the two-tier local government model, the SAV recommended that the Provincial People's Committee conduct reviews to establish the accountability of organizations and individuals involved in advising and submitting allocation norms to the Provincial People's Council before sufficient criteria and calculation bases had been established. It also recommended clarifying responsibility for issuing budget allocation decisions that were inconsistent with the Provincial People's Council's resolution on development investment expenditure allocation objectives for commune-level budgets.

For project management boards and project owners, the SAV recommended corrective action and lessons learned in investment project management, particularly in project formulation, appraisal and approval; contractor selection; contract management; construction quality and progress management; acceptance, payment, and investment finalization.

Regarding the Provincial People's Council, the SAV recommended that lessons be learned from issuing development investment expenditure allocation norms for commune-level budgets without sufficient allocation criteria, as well as from issuing Resolution No. 308/NQ-HDND dated October 17, 2025, which contained provisions that were not fully consistent.

The SAV also recommended that the Provincial People's Council direct its Economic and Budget Committee to review and draw lessons from the appraisal and examination of draft resolutions and the proposed revisions and additions to allocation norms submitted by the Provincial People's Committee before their issuance.

In particular, the SAV recommended that the Provincial People's Council strengthen its oversight of the implementation of VND 2.3 trillion in investment capital from the provincial budget allocated to communes, ensuring that the funds are used for the purposes approved by the Council.

Alongside the implementation of the financial recommendations, the audit findings highlight the need to further improve budget estimation, allocation, and utilization; strengthen the accountability of relevant agencies and units; and thereby enhance the effectiveness of public resource management and utilization at the local level.

16/11/2026 8
Despite spending 99.6% of its allocated budget for the 2025–2026 financial year, South Africa's Department of Sport, Arts and Culture (DSAC) has yet to address longstanding weaknesses in governance and financial controls. The Auditor-General of South Africa (AGSA) has warned that numerous gaps in the internal control system are increasing the risk of fraud, undermining budget efficiency and accountability.
View details
16/11/2026 6
On the afternoon of November 13, as part of his official visit and working trip to the Republic of Belarus, State Auditor General of Vietnam Nguyen Huu Nghia and his delegation held a bilateral meeting with Deputy Prime Minister of Belarus Aleksandr Terekhov, Head of the Belarusian delegation to the Vietnam–Belarus Intergovernmental Commission on Trade, Economic, Scientific and Technical Cooperation.
View details
13/11/2026 16
On November 12, in Minsk, the capital of Belarus, as part of an official working visit to the Republic of Belarus, a high-level delegation from the State Audit Office of Vietnam (SAV), led by Auditor General Nguyen Huu Nghia, held a bilateral meeting with the State Control Committee of the Republic of Belarus, headed by its Chairman, Vasily Gerasimov.
View details
13/11/2026 22
The rapid adoption of artificial intelligence (AI) across organizations is outpacing existing governance and control capabilities. The accelerated development of generative AI, AI agents, and the unauthorized use of AI tools (“shadow AI”) poses significant challenges related to transparency, data security, and accountability. In response to these emerging risks, internal audit functions must innovate their methodologies, enhance professional competencies, and strengthen oversight to ensure that AI applications are managed safely and effectively.
View details
12/11/2026 21
Disbursed investment capital from the state budget in the first 10 months of 2026 was estimated at VND 783.9 trillion, equivalent to 69% of the annual plan and up 19.8% year-on-year. Total registered foreign investment reached USD 54.85 billion, an increase of 74%, while disbursed foreign direct investment (FDI) amounted to USD 24.08 billion, up 13.1%. Increasing capital inflows are providing additional momentum for the economy. However, the key issue is not merely how much capital can be mobilized and disbursed, but more importantly, how much value, productive capacity, and competitiveness each unit of investment capital can generate.
View details
12/11/2026 20
The restructuring and streamlining of the political system's organizational apparatus, together with the implementation of the two-tier local government model, have resulted in adjustments to the functions, responsibilities, audited entities, and designated focal points of various agencies and organizations. Consequently, although many audits have been completed and recommendations issued, some recommendations may not yet have been fully implemented. It is therefore essential to ensure their timely and comprehensive handover and receipt to maintain continuity in monitoring, follow up on all outstanding recommendations, and prevent any omissions. The implementation of audit recommendations is a decisive factor in determining the effectiveness and efficiency of audit activities and serves as a basis for the State Audit Office of Vietnam (SAV) to demonstrate its performance and accountability to the National Assembly and the public.
View details
11/11/2026 30
The State Audit Office of Vietnam (SAV) is expected to strengthen data-driven auditing, remote auditing, thematic auditing and performance auditing in the coming years, with a particular focus on auditing public resources, development programs, nationally important projects and macroeconomic policies of the Party and the State, thereby serving the common interests of the country and its people.
View details
11/11/2026 21
Data should not only be regarded as a source of information for individual audits but also as a digital asset of the State Audit Office of Vietnam (SAV), requiring centralized management, consistent utilization and long-term reuse to support auditing activities, management, administration and strategic planning.
View details
10/11/2026 17
The Standing Committee of the Party Committee of the State Audit Office of Vietnam (SAV) has recently issued Official Letter No. 1614-CV/DU on communication activities commemorating the 80th anniversary of the First National Cultural Conference (November 24, 1946 – November 24, 2026), Vietnam Culture Day (November 24), and the Great National Unity Festival (November 18).
View details
10/11/2026 18
The State Audit Office of Vietnam (SAV) has recently published the results of a thematic audit on the management and use of public investment capital in Khanh Hoa Province during the 2021–2025 period. The audit revealed that 53 projects had to be suspended after their investment policies were approved; one project had achieved a disbursement rate of only 18.76% as of the audit date; and another project, scheduled for completion and handover in 2026, had only begun its investment preparation procedures by July 2026, when the audit was conducted.
View details
09/11/2026 38
On the morning of October 8, the Vietnam Association of Accountants and Auditors (VAA), in coordination with the Lao Cai Provincial Department of Finance, held the opening ceremony of a professional training conference on financial management for commune-level officials, civil servants, and public employees across the province at the Department of Finance's headquarters.
View details
09/11/2026 29
In its latest enforcement action, the State Securities Commission of Vietnam (SSC) has named several enterprises for violations involving periodic disclosure obligations, inaccurate information disclosure, securities issuance regulations, corporate governance reporting, and accounting personnel information.
View details
Head Office
Representative Office
Northern Branch
Ho Chi Minh City Branch
Key thời gian làm việc
Copyright © 2026 CPA VIETNAM AUDIT. All rights reserved. Website designed by Tat Thanh
Access statistics
Total visits: 487958 Currently visiting: 325
Website Policy